Bay of Biscay interconnector between Spain and France 70% complete; capacity to rise to 5 GW

The electricity link through the Bay of Biscay between Spain and France is 70% complete, Offshore Energy reports, based on progress updates from Red Eléctrica (REE) and RTE. Once the cable is operational, cross-border exchange capacity between the two countries will rise from 2.8 GW to 5 GW, almost doubling current transport capacity.

The project reportedly costs €3.1 billion, making it one of the largest interconnector investments in Europe. Offshore Energy is so far the only source for the 70% progress figure; REE and RTE have not separately confirmed that milestone, so it still counts as a single-source report.

An earlier statement from RTE itself does confirm the phasing: construction has been under way since October 2023, and at the end of May 2026, after a year of route preparation works, laying of the subsea cables began off Capbreton in the Landes region. That step is consistent with progress now, at the end of October, standing at 70%.

For market participants, the expansion matters because the current cross-border capacity of 2.8 GW has for years been a bottleneck in trading power between the Iberian Peninsula and the rest of the continent. Higher capacity would widen the scope for exporting Spanish solar and wind surpluses and importing French power (often nuclear-driven), which could increase price convergence between the two countries' day-ahead markets. No exact completion date for full operational status has been mentioned in the reporting.